Crusher run calculator for Nebraska
The locking base layer, calculated at finished compacted depth instead of an estimate from loose stone.
Enter your project dimensions
Crusher run settles 10-15% from its loose truck volume during compaction. Base your order on the measured finished depth, since a compacted layer can otherwise end up half an inch short. This calculator has the +10% allowance enabled for that purpose. It may also be called crush and run or 2 inch minus on some tickets. The material is crushed stone containing fines, about 3,000 lb per cubic yard, which compacts into a surface tires are less likely to displace.
Order for finished depth
- In feet, measure the pad dimensions or multiply the lane width by its length.
- Choose the finished compacted depth: use 4 inches for paths and pavers, 4-6 for driveways, and 6-8 where trucks travel.
- Divide cubic feet by 27 to get yards, then x 1.5 to find tons. Keep the +10% selected. Specs apply to the layer once it has been rolled.
Tons of coverage
| Compacted depth | 1 cubic yard covers | 1 ton covers |
|---|---|---|
| 2 inches | 162 sq ft | ≈ 108 sq ft |
| 4 inches | 81 sq ft | ≈ 54 sq ft |
| 6 inches | 54 sq ft | ≈ 36 sq ft |
| 8 inches | 41 sq ft | ≈ 27 sq ft |
Suitable uses and limits
- Driveway bases need 4-6 inches after compaction, with 2-3 inches of #57 or driveway gravel placed above for the travel surface.
- Crusher run by itself can form a usable surface for budget-minded rural lanes. Plan for dust in summer and reshaping every 2-4 years.
- For paver and slab work, compact 4 inches in 2-inch lifts. The Paver Base Calculator calculates the entire paver assembly.
- For shed and hot-tub pads, use 4 inches on stripped ground and 6 where the soil is soft.
- Keep crusher run out of a French drain. Its locking fines retain water, while drainage calls for clean #57 or drain rock.
Example: a 20 x 10 parking pad
For two hundred square feet at 4 inches compacted, 200 x 0.333 = 67 cubic feet = 2.5 cubic yards, or 3.7 tons. With the allowance, order 4 tons. Place and compact half the material, then repeat with the remainder. Two 2-inch lifts can last years longer than a single 4-inch pour, and renting a plate compactor for the afternoon costs less than the first pothole repair.
Delivery details
- Arrange for the base and surface stone together so the project can keep moving.
- Start with the pile at the far end of the run, then work back toward it as you spread. For large pads, moving downhill can save a full day.
- Lightly mist every lift ahead of compaction. Damp crusher run binds more firmly than dry material.
- Save a wheelbarrow-load for touch-ups. It is also used by road crews for pothole patching, and repairs may be needed later.
Pricing overview
Crusher run is made during crushing, rather than being washed and sorted stone. On a 4-ton order, the +10% allowance can help prevent the need for another half-ton delivery. Check the Crusher Run product page for the per-ton price, compare Road Base, and plan for both driveway layers together.
Crusher run and crush and run questions
What amount of crusher run is required for a driveway?
What is the weight of a yard of crusher run?
How do crusher run and gravel differ?
Are crush and run and crusher run identical?
Can crusher run serve as a finished surface?
How much will crusher run shrink during compaction?
More calculators
Base material calculation complete.
Crusher run sold by the ton, with free delivery.