Paver base calculator for Nebraska
Size the compacted stone layer below the pavers in tons, so the patio can stay level for five years.
Enter your project dimensions
The stone below pavers costs much less per square foot, yet trouble with a patio commonly starts in that lower layer. This calculator calculates compacted crusher run or a comparable blend at 1.5 tons per cubic yard: use 4 inches for foot traffic and 6-8 below cars. The +10% compaction allowance is selected by default. Calculate bedding sand separately as its required 1-inch layer.
Base sizing
- Measure the paver area in feet and carry the base 6 inches beyond each exposed edge. That extra base supports the edge restraint.
- Use 4 inches of compacted base for patios and walkways, 6 for clay soil or driveways, and 8 under driveways on soft ground.
- For tons, take cubic feet / 27 for yards, then x 1.5, with the +10% allowance on.
Excavation depth = base + 1" bedding + paver thickness − reveal
Project depth and coverage
| Project | Compacted base depth | 1 ton covers |
|---|---|---|
| Walkway or garden path | 4 inches | ≈ 54 sq ft |
| Patio or seating area | 4-6 inches | ≈ 43 sq ft |
| Driveway with cars | 6-8 inches | ≈ 31 sq ft |
| Clay or soft subgrade | add 2 inches + fabric | n/a |
Excavation layers from lawn to finished paver
Add all layer thicknesses to set the excavation depth. A usual patio has 4 inches of base, 1 inch of bedding sand, and a 2 3/8 inch paver flush with the lawn. That makes a 7.5-inch excavation, adjusted for the reveal above grade. Put the depth on a stake and check it during digging. Going too deep means paying to remove soil, with the Dirt Calculator run backward showing the yards leaving the hole, then paying again for stone to restore grade.
Paver base installation notes
- Compact the base in 2-inch lifts using a plate compactor, and lightly mist every lift. Base that is damp compacts tighter than dry material.
- Grade the compacted base at a 2-3% fall away from the house. The bedding sand and pavers will follow that grade.
- Place edge restraint over the compacted base, not lawn soil. The 6-inch extension gives it the needed support.
- For clay soil, put woven geotextile beneath the base. It keeps stone from working down into the subgrade through wet seasons.
- Do not use extra sand to replace base thickness. Sand shifts, which can leave a patio uneven.
Re-laying old pavers: check the base
Reworking a patio already in place? Its base may still be usable. Remove the pavers, scrape away the old bedding sand, then check the base. If it remains level, firm, and drains properly, install a new 1-inch bedding layer and the stone needed can be reduced to a tenth of what a new installation takes. In Nebraska's wetter loess ground, any low areas, soft sections, or pooled water mean removing the base as well. Leaving a failed base in place leads to the same problem beneath the replacement pavers.
Example: a 16 x 12 patio
Start with 192 square feet of paved area. Adding the 6-inch extension along three exposed sides makes the base area 210. For 4 inches compacted, 210 x 0.333 = 70 cubic feet = 2.6 cubic yards, about 3.9 tons, or 4.3 with allowance. Order 4.5 tons of crusher run and 0.9 tons of bedding sand from the Paver Sand Calculator in one free delivery. Arrange the drop after excavation, because stone left on grass for two weeks can kill a rectangle of lawn.
Questions on base depth, digging and tonnage
How much paver base do I need?
Is 2 inches of paver base sufficient?
What depth should paver base be?
How far down do pavers need to be excavated?
For paver base, crusher run or screenings?
Can pavers be installed without base?
More calculators
The base supports the paver surface.
Order crusher run and screenings by the ton with bedding sand.